Energy efficiency upgrade and expansion at Zumtobel plant in Usingen
30.04.2013
  • Lighting manufacturer invests 1.2 million euros in energy concept and factory hall expansion
  • Annual energy savings of approx. 25 per cent 
  • EU Green Building certification applied for

Dornbirn, Austria / Usingen, Germany – As part of a new energy concept, the lighting manufacturer Zumtobel has invested half a million euros in its Usingen production site. With a further investment sum of 700,000 euros, a covered area has been converted into a production hall. “These investments represent a clear commitment to the Usingen site and a major step towards conserving resources and protecting our climate,” says Operations Director Ralph Maier.

Energy concept successfully established
Annual energy savings of circa 25 per cent and a reduction in CO2 emissions of 450 tonnes per annum have been achieved with the new energy concept that was jointly developed with Siemens AG for Zumtobel’s Usingen plant. A key element of the energy efficiency upgrade is a combined heating and power (CHP) plant which as well as producing heat and electricity in a single process utilises natural gas with an overall efficiency rate of 91 per cent. Further measures have been implemented in addition to putting the efficient CHP plant into service. These include the changeover from oil to natural gas, requirements-based control of the heat supply, conversion of the heating system in the halls of the facility and replacement of the measuring, regulating and control technology. A green building monitor displays the amount of energy being consumed and generated on a continuous basis.

We began with the new energy concept in March 2012. On the basis of the data collected over the past year, we now intend to apply for the European Union’s Green Building Certificate,” explains Operations Director Ralph Maier.

Factory hall expansion to increase process efficiency
At the end of March, another step was taken towards modernising the luminaire plant in Usingen with the completion of the new Hall 5. A partially covered area has been extended within the past nine months to form a new production hall. The 700,000-euro investment means enhanced efficiency at the plant. Thanks to the new hall, manufacturing sections can be reorganised and transport routes shortened.

The Zumtobel lighting plant in Usingen – Facts and figures
Employees: approx. 180
Production area: approx. 8,000 m²
Focus: Medical suppy units and lighting solutions for the healthcare sector with a high percentage of custom manufacture (50 per cent), lighting solutions for offices
History: The Usingen plant has belonged to Zumtobel since 1979. After acquiring the production facilities of lighting manufacturer Disco Schneider & Co., Zumtobel extended its product portfolio in the area of medical supply units and lighting technology for healthcare applications.


Media contact
Astrid Kühn-Ulrich
Head of Corporate Communications
Tel. +43-(0)5572 509-1570
astrid.kuehn@zumtobel.com

Contact Zumtobel plant Usingen
Ralph Maier
Operations Director Zumtobel plant Usingen
Tel. +49 6081 1026 248
ralph.maier@zumtobel.com



pag_text_image - 0 7218



share it




Downloads

The Zumtobel lighting plant in Usingen invests in energy-efficient operations.

The Zumtobel lighting plant in Usingen invests in energy-efficient operations.

The new production hall means enhanced efficiency. Manufacturing sections have been reorganised and transport routes shortened.

The new production hall means enhanced efficiency. Manufacturing sections have been reorganised and transport routes shortened.

schließen
weiter
|
zurück
Zur Download-Liste hinzufügen